Flatiron Energy gets green light for 1.2GWh indoor BESS in Boston
System operator ISO New England has given the green light for a large, indoor BESS in Boston, Massachusetts, from developer Flatiron Energy.
System operator ISO New England has given the green light for a large, indoor BESS in Boston, Massachusetts, from developer Flatiron Energy.
System operator ISO New England has given the green light for a large, indoor BESS in Boston, Massachusetts, from developer
ISO New England has given the thumbs up to a project proposed by Flatiron Energy and envisaging the installation of a 300
The Commonwealth issued a draft request for proposals of 1.5 GW of batteries with storage durations of 4 to 10 hours, primarily funded through the state''s Clean Peak Standard.
Flatiron Energy has received approval from ISO New England for a 300-MW/1,200-MWh battery energy storage system in Boston, Massachusetts. The authorization includes the
With a clear goal of 5,000 MW by 2030 and a solid procurement plan, Massachusetts stands out as a prime market for energy storage technologies like lithium-ion,
Massachusetts is making a big push for batteries — not the kind you put in a flashlight, but powerful, tractor trailer-sized batteries that store energy for the electric grid.
The company has offices in Boston, New York City, and Boulder, Colorado and is currently developing energy storage systems in the Greater Boston, Connecticut, and New
With a clear goal of 5,000 MW by 2030 and a solid procurement plan, Massachusetts stands out as a prime market for
ISO New England has given the thumbs up to a project proposed by Flatiron Energy and envisaging the installation of a 300-MW/1,200-MWh battery energy storage
Flatiron Energy recently filed a Project Notification Form for “Project Lite Brite,” a 200-megawatt battery energy storage system (BESS) facility located in Brighton,
These BESS facilities are needed to support the state''s push to reduce fossil fuels and electrify buildings, with Boston this year
Flatiron Energy LLC, doing business as (d/b/a) Lite Brite Storage LLC (the “Proponent”), is proposing to construct a new two-storied battery energy
These BESS facilities are needed to support the state''s push to reduce fossil fuels and electrify buildings, with Boston this year enacting a net-zero requirement for new large real
The Commonwealth issued a draft request for proposals of 1.5 GW of batteries with storage durations of 4 to 10 hours, primarily funded
Flatiron Energy LLC, doing business as (d/b/a) Lite Brite Storage LLC (the “Proponent”), is proposing to construct a new two-storied battery energy storage facility at 35 Electric Avenue
PDF version includes complete article with source references.
Get specifications and technical data for our MW-scale energy storage and PV integration solutions.
45 Energy Innovation Park
London WC2H 8NA, United Kingdom
+44 20 7783 1966
Monday - Friday: 8:00 AM - 6:00 PM GMT